9.02.2013

{ KITCHEN: PROGRESS 2 }

…after the rough plumbing and electrical, drywall, and tiling were done, the cabinet and countertop installation began.




…once the countertop and backsplash were in, the back-painted glass backsplash was installed. after that, we installed the hood, shelves, magnetic knife strip, and spice racks.
 





…and finally, the drawer fronts and doors were installed.
 